ist 150 final

A(n) _____ on a project is a significant event that normally has no duration.
milestone
An IT company revises its process parameters in response to complaints from vendors that products were not ready on time. This would be an example of _____.
a corrective action
Which of the following are organizational process assets?
assets include formal and informal plans, policies, procedures, guidelines, information systems, financial systems, management systems, lessons learned, and historical information that can influence a project’s success.
Which of the following statements is true of project management?
It does not guarantee successes for all projects.
The outputs of the _____ process include change request status updates, project management plan updates, and project document updates.
monitoring and controlling
The _____ section of the project management plan describes specific methodologies a project might use and explains how to document information.
technical processes
Which of the following refers to a set of principles that guides decision making based on personal values of what is considered right and wrong?
ethics
Which of the following is true of return on investment or ROI?
it is always a percentage
Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?
project charter
Which of the following is true of a finsih-to-finish dependency?
It is a dependency in which the “from” activity must be finished before the “to” activity can be finished.
Which of the following is true of the agile approach to software development?
In the agile method, requirements and
solutions evolve through collaboration
Project procurement management primarily involves identifying stakeholder needs while managing their engagement throughout the life of the project.
false
In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.
controlling the schedule
A _____ is a tool used in quality management.
checklist
The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.
free slack
The first step in the planning process is _____.
to choose which projects to do and assigning resources to work on them
A network diagramming technique in which boxes represent activities is known as a(n) _____.
PDM
A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a ____ format
calendar
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float
longest and shortest
Payback occurs when
the net cumulative benefits equal the net cumulative costs.
Validated changes and validated deliverables are the outputs of the _____ subprocess of project quality management
monitoring and controlling
The formula to determine the number of communication channels is _____, where n is the number of people involved.
n(n-1)/2
The project team must take corrective action if stakeholders with high interest and high power are categorized as _____.
resistant
Which of the following is true about identifying stakeholder?
Stakeholders with indirect ties to the project need not be engaged with.
Using the formula for calculating the number of communication channels, how many channels would five people require?
10
After identifying and analyzing stakeholders, the project manager and team should develop a(n) ______ to help them effectively engage stakeholders and make sure that good decisions are made throughout the life of the project.
stakeholder management plan
The capacity to understand the motivations, intentions and desires of others is
interpersonal intelligence
The main outputs of the _____ process are team performance assessments and enterprise environmental factors updates.
developing the project team
Which of the following is a guideline that project managers should follow when communicating with their teams through e-mail?
If the entire message can fit in the subject line, put it there.
_____ helps integrate traditionally separate organizational functions, set process improvement goals and priorities, provide guidance for quality processes, and provide a point of reference for appraising current processes.
CMMI
_____ involves using punishment, threats, or other negative approaches to get people to do things they do not want to do
coercive power
_____ applies to positive risks when the project team cannot or chooses not to take any actions toward a risk.
Risk Acceptance
_____ involves determining everyone involved in the project or affected by it, and determining the best ways to manage relationships with them.
Identifying stakeholders
One of the main outputs of the process are the issue logs
managing stakeholder engagement
_____ address where the project stands in terms of meeting scope, time, and cost goals.
Status reports
A(n) _____ is a column chart that shows the number of resources assigned to a project over time.
resource histogram
_____ involves deciding how to approach and plan the risk management activities for the project.
Planning risk management
The stakeholder register is the output of the _____ process of project stakeholder management
executing
Performing qualitative and quantitative risk analyses are subprocesses of the _____ process of project risk management
planning
Recognizing an employee as the “Star Performer of the Month” would be satisfying the _____ need of the Maslow’s hierarchy of needs.
esteem
Six Sigma’s target for perfection is the achievement of no more than _____ defects, errors, or mistakes per million opportunities
3.4
_____ is a technique for resolving resource conflicts by delaying tasks.
resource leveling
Doctors who have been co-opted to actively participate in a project related to using information technology for chronic health problems would be examples of _____ stakeholders.
leading
_____ addresses the ease of performing maintenance on a product
maintainability
____ describe what the project team has accomplished during a certain period.
progess reports
_____ involves allocating ownership of the risk to another party
Risk sharing
A(n) _____ refers to a product or service, such as a technical report, a training session, a piece of hardware, or a segment of software code, produced or provided as part of a project.
deliverable
_____ are an example of external stakeholders for an organization.
competitors
Project procurement management mainly involves:
buying goods and services for a project from outside the performing organization.
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
feeding buffers
In organizational culture, people focus refers to _____.
the degree to which management’s decisions take into account the effect of outcomes on employees within the organization
Which of the following is true of the project life cycle?
In the early phases of a project life cycle, resource needs are usually lowest.
A _____ is an organizational group responsible for coordinating the project management function throughout an organization.
Project Management Office
Which of the following dependencies involve relationships between project and non-project activities?
External
In the _____ model, developers use a model to generate functional requirements and physical design specifications simultaneously.
prototyping life cycle
In which of the following areas of management is payback analysis most likely to be used?
cost
After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to:
estimate the duration of activities.
Project _____ management ensures that the project will satisfy the stated or implied needs for which it was undertaken.
quality
In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work
defining activities
The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.
crashing
Which of the following is an output of schedule control?
Lessons-learned reports
Which of the following is a difference between projects and operations?
Projects are temporary endeavors whereas an organization’s operations are ongoing in nature.
Those who are _____ have a higher tolerance for risk, and their satisfaction increases when more payoff is at stake
risk-seeking
_____ involves eliminating a specific threat, usually by eliminating its causes.
Risk avoidance
A _____ is a graphic display of data that illustrates the results of a process over time
control chart
_____ involves doing whatever you can to make sure the positive risk happens
Risk exploitation
The _____ process is often associated with the technical tools and techniques of quality management, such as Pareto charts, quality control charts, and statistical sampling.
quality control
_____ is the degree to which a system performs its intended function
Functionality
An example of push communication is _____.
voice mails
Performing quality assurance is a subprocess of the _____ process of project quality management.
executing
_____ analysis simulates a model’s outcome many times to provide a statistical distribution of the calculated results.
monte carlo
At the bottom of Maslow’s structure are _____ needs
physiological
_____ means that a product can be used as it was intended.
Fitness for use
_____ involves determining which risks are likely to affect a project and documenting the characteristics of each.
Identifying risks
Key outputs of _____ process are project staff assignments, resource calendars, and project management plan updates
managing the project team
_____ is the new knowledge area identified by the Project Management Institute.
Project stakeholder management
_____ are unplanned responses to risk events used when project teams do not have contingency plans in place
workarounds
_____ involves monitoring stakeholder relationships and adjusting plans and strategies for engaging stakeholders as needed.
Controlling stakeholder engagement
_____, a quality system standard is a three-part, continuous cycle of planning, controlling, and documenting quality in an organization
ISO 9000
Managers who follow _____ assume that the average worker wants to be directed and prefers to avoid responsibility.
Theory X
According to McClelland’s acquired-needs theory, people with a high need for _____ desire harmonious relationships with other people and need to feel accepted by others.
affiliation
_____ is based on an individual’s personal charisma
referent power
In the Tuckman model, _____ occurs when the emphasis is on reaching the team goals, rather than working on team process
performing
A ____ is a bell-shaped curve that is symmetrical regarding the average value of the population (the data being analyzed).
normal
According to Herzberg, which of the following is a motivational factor?
Recognition
A(n) _____ is any instance where the product or service fails to meet customer requirements
defect
_____ are/is a qualitative risk analysis tool that maintains an awareness of risks throughout the life of a project in addition to identifying risks
Top Ten Risk Item Tracking

Need essay sample on "ist 150 final"? We will write a custom essay sample specifically for you for only $ 13.90/page

Can’t wait to take that assignment burden offyour shoulders?

Let us know what it is and we will show you how it can be done!
×
Sorry, but copying text is forbidden on this website. If you need this or any other sample, please register

Already on Businessays? Login here

No, thanks. I prefer suffering on my own
Sorry, but copying text is forbidden on this website. If you need this or any other sample register now and get a free access to all papers, carefully proofread and edited by our experts.
Sign in / Sign up
No, thanks. I prefer suffering on my own
Not quite the topic you need?
We would be happy to write it
Join and witness the magic
Service Open At All Times
|
Complete Buyer Protection
|
Plagiarism-Free Writing

Emily from Businessays

Hi there, would you like to get such a paper? How about receiving a customized one? Check it out https://goo.gl/chNgQy

We use cookies to give you the best experience possible. By continuing we’ll assume you’re on board with our cookie policy