Project Cost Management – Ch 7 (True/False)

Overrun is the additional percentage amount by which estimates exceed actual costs.
False
The primary output of the planning cost management process is a change request.
False
IT project managers must be able to present and discuss project information both in financial and technical terms.
True
Project managers must conduct cash flow analysis to determine net present value.
True
Intangible costs can be easily measured in monetary terms.
False
When deciding what projects to invest in or continue, one should include sunk costs.
False
It is important for project managers to focus on indirect costs because they can be easily controlled.
False
If an important supplier goes out of business, management reserves can be set aside to cover the resulting costs.
True
Contingency reserves are also known as unknown unknowns.
False
A cost management plan can include organizational procedures links, control thresholds, and process descriptions.
True
A budgetary estimate is the most accurate of the three types of estimates.
False
Budgetary estimates are made even before a project is officially started.
False
Definitive estimates are made one year or less prior to project completion.
True
Estimates should become more accurate as time progresses.
True
Supporting details for an estimate include the ground rules and assumptions used in creating the estimate.
True
Analogous estimates are called activity based costing.
False
Analogous estimates are the most accurate technique to estimate costs.
False
In a bottom up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates.
True
Parametric models are reliable when the models are flexible in terms of the project’s size.
True
One of the reasons why project cost estimates are inaccurate is because human beings are biased toward underestimation.
True
It is important for project managers to understand that every cost estimate is unique.
True
Determining the budget involves allocating the project cost estimate to individual work items over time.
True
The project management plan and project funding requirements are inputs of the process of controlling costs.
True
The formulas for variances and indexes start with EV, the earned value.
True
If cost variance is a positive number, it means that performing the work costs more than planned.
False
A negative schedule variance means that it took lesser than planned to perform the work.
False
If the cost performance index (CPI) is less than 100 percent, the project is under budget.
False
A schedule performance index of one means that the project is on schedule.
True
In an earned value chart, when the actual cost line is right on or above the earned value line, it indicates that costs are less than planned.
False
Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
True

Need essay sample on "Project Cost Management – Ch 7 (True/False)"? We will write a custom essay sample specifically for you for only $ 13.90/page

Can’t wait to take that assignment burden offyour shoulders?

Let us know what it is and we will show you how it can be done!
×
Sorry, but copying text is forbidden on this website. If you need this or any other sample, please register

Already on Businessays? Login here

No, thanks. I prefer suffering on my own
Sorry, but copying text is forbidden on this website. If you need this or any other sample register now and get a free access to all papers, carefully proofread and edited by our experts.
Sign in / Sign up
No, thanks. I prefer suffering on my own
Not quite the topic you need?
We would be happy to write it
Join and witness the magic
Service Open At All Times
|
Complete Buyer Protection
|
Plagiarism-Free Writing

Emily from Businessays

Hi there, would you like to get such a paper? How about receiving a customized one? Check it out https://goo.gl/chNgQy

We use cookies to give you the best experience possible. By continuing we’ll assume you’re on board with our cookie policy