Most trade schools, colleges, and universities did not start offering degrees in computer technology, computer science, management information systems, or other information technology areas until the ____.
a. 1950s
b. 1970s
c. 1980s
d. 1990s
b
Projects involve ____ project management process groups.
a. three
b. five
c. eight
d. ten
a
____ include defining and authorizing a project or project phase.
a. Initiating processes
b. Planning processes
c. Executing processes
d. Monitoring and controlling processes
b
____ include devising and maintaining a workable scheme to ensure that the project addresses the organization’s needs.
a. Initiating processes
b. Planning processes
c. Executing processes
d. Monitoring and controlling processes
b
Examples of ____ include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements.
a. monitoring and controlling processes
b. executing processes
c. planning processes
d. initiating processes
c
A common ____ is reporting performance, where project stakeholders can identify any necessary changes that may be required to keep the project on track.
a. executing process
b. closing process
c. monitoring and controlling process
d. planning process
d
Administrative activities are often involved in ____, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project.
a. monitoring and controlling processes
b. executing processes
c. initiating processes
d. closing processes
a
During ____ processes for a new project, the organization recognizes that a new project exists, and completes a project charter as part of this recognition.
a. initiating
b. planning
c. opening
d. controlling
b
____ is crucial in information technology projects because once a project team implements a new system, it takes a considerable amount of effort to change the system.
a. Initiating
b. Planning
c. Executing
d. Closing
a
The project integration management knowledge area maps to the ____ process group through the activities of developing project charters.
a. initiating
b. planning
c. executing
d. monitoring and controlling
d
The project scope management knowledge area maps to the ____ process group through the activities of scope verification and scope control.
a. initiating
b. planning
c. executing
d. monitoring and controlling
d
The project time management knowledge area maps to the ____ process group through the activity of schedule control.
a. initiating
b. planning
c. executing
d. monitoring and controlling
b
____ is a planning process falling under the Project Integration Management knowledge area.
a. Schedule development
b. Develop project management plan
c. Create WBS
d. Quality planning
c
____ is a planning process falling under the Project Scope Management knowledge area.
a. Schedule development
b. Develop project management plan
c. Create WBS
d. Quality planning
d
____ is a monitoring and controlling process.
a. Develop project team
b. Request seller responses
c. Risk response planning
d. Integrated change control
b
The project cost management knowledge area maps to the ____ process group through the activities of estimating costs and budget determination.
a. initiating
b. planning
c. executing
d. monitoring and controlling
c
The project communications management knowledge area maps to the ____ process group through the activity of information distribution.
a. initiating
b. planning
c. executing
d. monitoring and controlling
d
The project procurement management knowledge area maps to the ____ process group through the activity of administering procurements.
a. initiating
b. planning
c. executing
d. monitoring and controlling
c
The project procurement management knowledge area maps to the ____ process group through the activities conducting procurements.
a. initiating
b. planning
c. executing
d. monitoring and controlling
c
____ is an iterative software development process that focuses on team productivity and delivers software best practices to all team members.
a. RAP
b. RIP
c. RUP
d. ROP
a
____ should serve as the foundation for deciding which projects to pursue.
a. Strategic planning
b. Project managers
c. Successful past projects
d. Employee abilities
b
An organization may initiate information technology projects for several reasons, but the most important reason is to support ____.
a. financial security
b. business objectives
c. technological advances
d. shareholders
a
A ____ is a document that includes details related to the identified project stakeholders.
a. stakeholder register
b. stakeholder list
c. stakeholder directory
d. stakeholder contact list
c
A ____ is an approach to help increase the support of stakeholders throughout the project.
a. stakeholder management plan
b. stakeholder strategy
c. stakeholder management strategy
d. stakeholder management list
c
A ____ is a meeting held at the beginning of a project so that stakeholders can meet each other, review the goals of the project, and discuss future plans.
a. kick-off party
b. launch meeting
c. kick-off meeting
d. project launch meeting
b
The ____ is often held after the business case and project charter are completed, but it could be held sooner, as needed.
a. kick-off project
b. kick-off meeting
c. launch meeting
d. launch project
d
It is good practice to focus on the ____ of meetings.
a. flow
b. planning
c. agenda
d. results

Need essay sample on "SPM-CHAP 3"? We will write a custom essay sample specifically for you for only $ 13.90/page

Can’t wait to take that assignment burden offyour shoulders?

Let us know what it is and we will show you how it can be done!
×
Sorry, but copying text is forbidden on this website. If you need this or any other sample, please register

Already on Businessays? Login here

No, thanks. I prefer suffering on my own
Sorry, but copying text is forbidden on this website. If you need this or any other sample register now and get a free access to all papers, carefully proofread and edited by our experts.
Sign in / Sign up
No, thanks. I prefer suffering on my own
Not quite the topic you need?
We would be happy to write it
Join and witness the magic
Service Open At All Times
|
Complete Buyer Protection
|
Plagiarism-Free Writing

Emily from Businessays

Hi there, would you like to get such a paper? How about receiving a customized one? Check it out https://goo.gl/chNgQy

We use cookies to give you the best experience possible. By continuing we’ll assume you’re on board with our cookie policy